remains on schedule at HS, K-8 facility
GREENVILLE – “So far the timelines are as expected,” said Greenville
City Schools Superintendent Doug Fries. In the District’s second full
week of school the high school is in its second phase of construction
and the ‘early site work’ at the K-8 location is almost ready to be
‘stoned.’
“The earthwork is almost finished (on North Ohio Street),” Fries said.
Next will be hard compacting of the dirt, followed by a layer of stone.
“That will be the building pad; it will occur in about two weeks.” He
said temporary utilities and the foundation package comes next, noting
that should be early in October.
Fries said work is continuing on the roof and the cafeteria expansion.
Phase 1, the administration area, music areas and hallway are finished.
They’re waiting on some flooring that was back-ordered. Water lines in
the area are complete.
Phase 2 addresses four rooms on the second floor; when that is complete
work will move across the hall to another four or five rooms. Each
phase runs 5-6 weeks; when one is completed classrooms are shifted and
the next phase begins...