Ohio Supreme
Court...
State ordered to
compensate owners for
Land ‘Taking’
December 2, 2011
State Ordered
to Compensate Owners for
‘Taking’ of Land Caused by Overflows from Grand Lake St. Marys. Court
Finds 1997
Changes to Spillway Increased Downstream Flooding.
(Dec. 1, 2011)
The Supreme Court of
Ohio today issued a writ of mandamus ordering the Ohio Department of
Natural
Resources (ODNR) to commence appropriation proceedings to compensate
the owners
of land west of Grand Lake St. Mary’s for a “taking” of their property
caused
by increased overflows from the lake into Beaver Creek.
The Court’s
7-0 decision, authored by
Justice Yvette McGee Brown, found that the state’s 1997 widening of the
western
spillway from the lake into the surrounding watershed caused a
significant
increase in the frequency, severity and duration of flooding of
downstream
properties, to the detriment of the owners of those properties.
In reaching
today’s ruling, the Court
held that although lawsuits alleging a physical or regulatory taking of
real
property must generally be brought within four years of the injurious
conduct,
that statute of limitations is tolled (does not run) when the effect of
an
actor’s conduct on its own land is of a continuing nature, and the
conduct
causes recurring damage to another’s property.
The Court held
further that, in
eminent-domain cases involving claims of government-induced flooding,
the
claimant can establish a taking of property by proving: (1) that the
flooding
is either intended by the government or is the direct, natural or
probable
result of governmental activity, and (2) the flooding is either a
permanent
invasion or creates a permanent liability because of intermittent but
inevitably recurring overflows.
The case
involved a dispute between
ODNR and the owners of more than 80 properties in Mercer County that
border
Beaver Creek along a 10-mile reach from the western spillway of Grand
Lake St.
Marys to the confluence of Beaver Creek into the Wabash River near the
Ohio/Indiana border. The parties identified in the case caption are one
of the
property owners, Wayne Doner, and former ODNR director Scott A. Zody.
The property
owners alleged that since
ODNR replaced a former 39-foot-wide spillway at the western end of the
lake
with a new 500-foot-wide spillway in 1997, the owners’ land has been
subject to
repetitive flooding that is more frequent, more severe, more
long-lasting and
more damaging to their ability to use it for agriculture or other
purposes than
was the case before the spillway was widened. They asserted that,
despite
advance warnings about the consequences of widening the spillway and
repeated
demands by the owners since the spillway was widened that ODNR take
action to
alleviate the increased flooding, the department has refused to: 1)
make any
adjustment to the spillway or its lake-level management practices, or
2) take
legal action to appropriate their land and compensate them for the loss
of its
use.
In 2009 the
property owners filed an
original action in the Supreme Court of Ohio seeking
a writ of mandamus that would compel the
state to appropriate their land and compensate them for the loss of its
use
under Ohio’s eminent domain laws.
Writing for
the Court in today’s
decision, Justice McGee Brown began by rejecting the state’s argument
that the
property owners had missed the four-year statute of limitations (time
limit)
for filing suit based on an alleged taking of private property under
R.C.
2305.09(E), because they failed to file their complaint within four
years after
the spillway expansion was completed in 1997.
Citing three
prior Supreme Court of
Ohio decisions, Valley Railway Co. v. Franz (1885), State v. Swartz
(2000) and
Sexton v. Mason (2008), Justice McGee Brown wrote: “Sexton, Valley Ry.,
and
Swartz lead inexorably to the conclusion that when an act carried out
on the
actor’s own land causes continuing damage to another’s property, and
the
actor’s conduct or retention of control is of a continuing nature, the
statute
of limitations is tolled. There is no logical rationale for refusing to
apply
this rule to takings cases and R.C. 2305.09(E). Otherwise, a person
whose
property is damaged by flooding caused by another’s actions might have
a cause
of action against a private person or entity but not against a
governmental
entity. Here, respondents constructed the new spillway in 1997 and
continued to
exercise control over both the spillway and the lake level by making
decisions
not to draw down the water either annually or before heavy rains.
Therefore,
based on this court’s precedent, relators’ mandamus claim is not barred
by the
four-year statute of limitations in R.C. 2305.09(E), because
respondents’
ongoing control has tolled the running of the limitations period.”
In concluding
that the property owners
had met their burden of showing that the increased flooding of their
land was
caused by the spillway expansion, Justice McGee Brown wrote: “First,
relators
presented substantial, credible, and uncontroverted firsthand
testimonial and
documentary evidence that following the respondents’ construction of
the new
spillway in 1997 and its subsequent abandonment of lake-level
management, their
properties flooded more frequently, over a larger area, for longer
duration,
and with greater damage.
“Second,
relators’ primary expert,
engineer Pressley L. Campbell, testified that the redesigned spillway
caused
frequent and severe flooding in the Beaver Creek-Wabash River area.
This
flooding would have been ‘highly unlikely, if not impossible’ without
the new
spillway and respondents’ subsequent failure to manage the lake level.”
“Third, the
reliance of respondents
and their expert on a 1981 U.S. Army Corps of Engineers report to
discount
Campbell’s expert opinion is misplaced. According to engineer James
Moir, the
current conditions differ from those in existence when that report was
completed. The conditions are now very different. There are now no
trees along
Beaver Creek, and thus the creek has a much greater capacity to convey
water
than it had previously.”
“Fourth,
significantly, respondents’
own expert, Stantec, concluded in its hydrologic and hydraulic analysis
that
for the 15-year rain event that respondents claim to be the applicable
frequency for a takings analysis, ten of relators’ parcels suffered
increased
maximum depth and duration of flooding and 46 of their parcels
experienced
increased duration of flooding since the redesign of the spillway and
the
abandonment of lake-level management. That is, even Stantec concedes
that
flooding of at least some of relators’ property was caused by the new
spillway
and the lack of lake level management.”
“Fifth,
Stantec also concluded that
the peak flow from the new spillway in even ten-year rain events now
exceeds
the peak flow from historical 100-year events with the old spillway.”
“ ... Based on
the foregoing, this
case is not barred by the four-year statute of limitations of R.C.
2305.09(E),
and relators have established that respondents’ construction of the
spillway
and concomitant refusal to lower the lake level at GLSM caused flooding
with
the requisite frequency to constitute a taking. ...
Respondents were free to determine that the
old spillway needed to be replaced for the dam at GLSM to survive a
probable
maximum flood. And they were also authorized to determine that
redesigning the
spillway and abandoning lake-level
management
were the preferable ways to remedy the probable-maximum-flood problem
and to
appeal to both recreational users of the lake and homeowners on the
southern
shore of the lake. Once they made that decision, however, they were
liable for
the damage to downstream landowners caused by the intermittent, but
inevitably
recurring, flooding that resulted from the new western spillway.”
“Therefore, we
grant a writ of
mandamus to compel respondents to commence appropriation proceedings to
determine the amount of their taking of the property.”
2009-1292. State ex rel. Doner v. Zody, Slip Opinion No.
2011-Ohio-6117.
In Mandamus.
Writ granted.
O’Connor,
C.J., and Pfeifer, Lundberg
Stratton, O’Donnell, Lanzinger, and Belfance, JJ., concur.
Eve V.
Belfance, J., of the Ninth
Appellate District, sitting for Cupp, J.
Note: Opinion
summaries are prepared
by the Office of Public Information for the general public and news
media.
Opinion summaries are not prepared for every opinion released by the
Court, but
only for those cases considered noteworthy or of great public interest.
Opinion
summaries are not to be considered as official headnotes or syllabi of
Court
opinions. The full text of this and other Court opinions from 1992 to
the
present are available online from the Reporter of Decisions. For more
informaton, click here
For pdf of
opinion, click here
|