3D
scale modeling planned for K-8 building By
Bob Robinson
GREENVILLE
– Bruce Miller of Garmann Miller Architects Engineers, Minster,
told Greenville City School District Superintendent Doug Fries, other
school officials and board members, and Ohio Facility Construction
Commission (OFCC) representatives of the company’s plans to use 3D
scale modeling for the district’s recently approved K-8 building
project on North Ohio Street.
“This
will be the fourth school we’ll have used it for,” Miller said in
a phone interview. The first one was two years ago. “Greenville
will be the largest.”
Miller
noted he didn’t think there would be a problem using the software
program in the planning stage but was seeking approval from the
commission to use it in the field.
“Our
goal is to allow us to use it from start to finish,” Miller told
OFCC representatives Wayne Coleman and Nathan Jones Sept. 20 in the
Anna Bier Room at Henry St. Clair Memorial Hall.
“It
makes a huge difference,” Miller said. With 3-D scale modeling they
can see where every pipe goes, every fitting, every concrete block…
if a pipe is crossing where it isn’t supposed to, they can catch it
and fix it before it ever gets to the construction stage.
“The
model tells you exactly how many blocks are in the building. There’s
no guesswork.” Miller added there is no additional cost to the
district. The company absorbs it but it saves time in the field with
mistakes.
“Just
knowing the exact number of concrete blocks that will be needed in
one project saved over $100,000,” he said.
OFCC’s
Coleman said from their perspective they have to look at the various
issues involved, but added they didn’t want to delay the process.
“It’s a tremendous step to take that kind of leap into that
expense,” he added.
“This
is a bigger project,” Miller responded. “It will be using bigger
players who can use it as a construction tool.” He noted the
construction manager would be working with the owners, OFCC and
Garmann Miller to build the project.
“For
a project like this, we pre-qualify the players,” he said. For
those not used to 3D modeling, traditional 2D line drawings still
allow them to see the scale.
Miller
noted when it was used in the past it has gone well.
“When
we did Kenton (City Schools) there were no problems. It was
surprising how close the numbers came in. Just catching two or three
things could save a couple hundred thousand dollars. It’s better;
more complete.”
Miller
told the group they were still in the discussion stage regarding
specific plans for the school. There will likely be two wings on two
floors: K-2 lower level with 3-4 above in one wing; 5-6 lower level
with 7-8 above in the other.
Questions
that need to be addressed include administration, possibly to
separate the two wings; the gymnasium, media center that needs to be
flexible, security, access points, bus issues and more.
“We
have an old traffic study,” Miller said, noting it was dated 2002.
“We’ll need an updated one. We’ve had meetings with the city,
with ODOT (Ohio Department of Transportation)… There are no
sidewalks, so we’re looking for grants.”
He
added release time shouldn’t be a big issue, but parent pickups are
always a concern.
“They
are the worst at reading signs,” he said.
Miller
noted every community is different. “Do we want a conservative
look? Cutting edge? Or do we want the more traditional educational
look?” These areas still need to be explored.
Coleman
asked if the (Greenville) district seemed amenable to 21st Century
technology.
“Yes,”
Miller responded, but noted if the district really wants to get into
the 21st Century, people can be brought in.
There
was discussion about how often Garmann Miller would be on site.
“We’ll
be here for the important things, like starting on the roof… things
like that,” Miller said. “Also we’ll be here for the high
school so we can go to the other site.
“There
is a lot of incentive for everyone to get along at the job site. We
work well or we lose money. We have to trust each other… start to
finish. There will be problems. We resolve them, the sooner the
better.”
Coleman
responded, “There is a certain amount of trust… but we are the
owners.”
Miller
said later construction on the K-8 building can begin as early as
late summer 2014 and will take approximately two years to complete.
“This
is too important,” he said. “We don’t want to rush it.”
Published
courtesy of The Early Bird
|